NORTH LANDFILL |
|
The Stora Enso pulp mill's 20 year old north landfill was scheduled for closure after the nearby Bearhead landfill was opened. Monitoring wells were constructed and a monitoring program for storm water, leachate, groundwater, and gas vectors was initiated. Innovative use of mill residuals (ash & sludge) as a hydraulic barrier material was prototype tested and incorporated in the design. A prototype 8 Ha capping section comprising of 4 test cells was constructed and monitored in the autumn of 2001. Based on supportive results the capping operation now utilizes the residual waste products.
C.J MacLellan & Associates Inc.![]() 65 Beech Hill Road, Suite 2 Antigonish, Nova Scotia, CA B2G-2P9 Ph: (902) 863-1220 Fax: (902) 863-3225 |